5/4/16
left side of the engine compartment complete.
With the actual frame portion of the lower engine compartment done it was time to get the upper closing walls finished.
Part of it was also finish out the upper corner of the lid opening where the cowl and quarter panel meet. Finish the joint, plug-welds and trim off the flange excess.
Not 100% but the heavy lifting at least done to this small area.
Next was buttoning up that long weld joint where I had to make the height adjustment for the mating flange. That sucked...
Then it was onto finishing up the welds up to the firewall.
Middle to left side complete. Doesn't look like much but a lot attention required to finish out all the twists and turns. These are areas that are so hard to stay motivated to finish but its such a relief once its all behind you.
Thanks for looking!
Justin
left side of the engine compartment complete.
With the actual frame portion of the lower engine compartment done it was time to get the upper closing walls finished.
Part of it was also finish out the upper corner of the lid opening where the cowl and quarter panel meet. Finish the joint, plug-welds and trim off the flange excess.
Not 100% but the heavy lifting at least done to this small area.
Next was buttoning up that long weld joint where I had to make the height adjustment for the mating flange. That sucked...
Then it was onto finishing up the welds up to the firewall.
Middle to left side complete. Doesn't look like much but a lot attention required to finish out all the twists and turns. These are areas that are so hard to stay motivated to finish but its such a relief once its all behind you.
Thanks for looking!